Firewater Hydrants / Valve Replacements

Firewater Hydrants / Valve Replacements Scope of Project: Shoring / Excavations / Fusing / HEIs / Bolt-ups / Backfill Location and Year: Suncor East Tank Farm – 2020 to current Project Challenges and Solutions: Rotaflow was asked to replace numerous Hydrants and Valves in the ETF. The scope had to be done in sequence, so […]
28″ HDPE / 24″ CS Firewater Jumper Line

28″ HDPE / 24″ CS Firewater Jumper Line Scope of Project : Excavation / Shoring / Fusing / HDD (Horizontal Directional Drilling ) / Hydro-Testing / HEI’s / Tie-ins / Bolt Ups / Backfill / Cathodic Protection / Frost Protection Location and Year : Suncor Firebag – 2023 Project Challenges and solutions : Rotaflow was […]
Sanitary Sewer Repair
Sanitary Sewer Repair Scope of Project: Shoring / Excavations / Pipe Bursting / Isolation bags / Fusing / HEI’s / Monitoring / Backfill Location and Year: Suncor Base Plant – 2022 Project Challenges and Solutions: Rotaflow was awarded the SOW to repair a damaged section of the sanitary sewer system, which was on […]
Industrial Sewer Repair
Industrial Sewer Repair Scope of Project: Shoring / Excavations / lining the interior of the Pipe / Isolation bags / HEI’s / Monitoring / Backfill Location and Year: Suncor Base Plant – 2023 Project Challenges and Solutions: Rotaflow was awarded the SOW to repair a damaged section of the industrial sewer system, This […]
Temporary Drain Project
Temporary Drain Project Scope of Project: Fusing / Fabrication / Installation Location and Year: Albian Sands – 2023 Project Challenges and Solutions: Rotaflow was awarded the SOW to fuse 12” and 20” HDPE lines around a Tank for drainage. The challenges were working under pipe racks a go nd multiple trades taking a tank down. […]
Potable Water Re-Route
Firewater Hydrants / Valve Replacements Scope of Project: Shoring / Excavations / Fusing / HEIs / Bolt-ups / Backfill Location and Year: Suncor East Tank Farm – 2020 to current Project Challenges and Solutions: Rotaflow was asked to replace numerous Hydrants and Valves in the ETF. The scope had to be done in sequence, so […]
Fire System Maintenance for an Oil & Gas and Mining Site

Fire System Maintenance for an Oil & Gas and Mining Site Scope of Work- Fire Alarm Inspected and test Fire Alarm system to the requirement of the Alberta Fire Code and in conformance with CAN/ULC-S536, Inspection and Testing of Fire Alarm Systems and CAN/ULC-S561, “Installation and Services for Fire Signal Receiving Centers and Systems.” Provide […]
Arc Flush Study for the Installation of Permanent Power in Tailing Facility

Arc Flush Study for the Installation of Permanent Power in Tailing Facility Scope of Work- Rotaflow conducted an arc flash study for the installation of permanent power for an Oil & Gas Tailings facility which encompasses the circuit breaker at switchgear and all downstream equipment including MFT drying and MPSU polymer system. This study provided […]
Detailed Electrical & Instrumentation Engineering Design for a Cold Process Water Unit

Detailed Electrical & Instrumentation Engineering Design for a Cold Process Water Unit Scope of Work- Rotaflow performed a Pre-DBM study for Gland and Tempering Water Pumping System for an Oil & Gas upstream Plant Cold Process Water unit(CPW) for an Oil & Gas upstream unit Cold Process Water unit. The process study provided engineering recommendations […]
Modification of Existing Barges – Oil Sand Mining Facility

Modification of Existing Barges – Oil Sand Mining Facility Scope of Work- Replacement of existing pump/motors located on the electric Barge and installation of six vertical turbine water pump/motor assembly, Knife gate valves with Electrical actuators, Magnetic/Cidra flow meters and pressure transmitters along with Pressure gauges. Instrumentation on pond water lines was needed to control […]