Main Fire Water Pump Replacement

Main Fire Water Pump Replacement Project Undertook the entire GC scope including engineering and procurement support, construction and commissioning (Replacement in Kind) of 5000gpm Fire Water Pump House. Project came in 1% under budget No safety incidents or issues arose during the project Many changes during the project execution

Flow Testing

Rotaflow Flow Testing All fire pumps are required by code to be annually tested to confirm their performance. This video is an annual flow test of a fire pump using our flow test trailer. The flow test trailer provides accurate results, decreases overall test time, and de-chlorinates testing water

Suncor Fire Water Pump House Construction

Suncor Fire Water Pump House Construction

Suncor Fire Water Pump House Construction Rotaflow was awarded this scope by Suncor in 2018 to replace three existing firewater pump systems at a Firewater pump house located in northern Alberta. This included replacing gear drives, diesel engines, pump controllers, diesel fuel storage tanks and associate equipment, modification of existing pump house building, pump pad […]

Suncor Foam Suppression System Upgrade

Suncor Foam Suppression System Upgrade Rotaflow was awarded this turnkey project in 2019 to upgrade the foam suppression system at one of the Suncor plants in Northern Alberta. The scope included replacement of two foam concentrate pumps, controllers, motors, valves, instruments, electrical cables, modification of pump pads, modification and re-routing of piping, updating fire alarm […]

TC Energy Firewater Pump House Sprinkler System Design

fire pump house

TC Energy Firewater Pump House Sprinkler System Design Rotaflow was awarded this scope by TC Energy in 2019 to provide engineering design for sprinkler system of a fire pump house in one of their facilities in Northern Alberta. This included preparation of layout drawings and hydraulic calculation for the sprinkler system, conducting sprinkler system commissioning […]

Suncor Fire Water Pumps Replacement

Fire water pump house with red firewater piping and pumps at Suncor

Suncor Fire Water Pumps Replacement Rotaflow was awarded the scope by Suncor in 2019 to assess the condition of fire water pumps in two plants in Northern Alberta and identify if they reached their end of the life cycle. As per the finding of this assessment, Rotaflow was awarded to proceed with the replacement of […]

Fort Hills Fire Protection System Commissioning and Maintenance

Fort Hills Fire Protection system Commissioning and Maintenance Rotaflow was awarded the scope to undertake the commission of the fire protection system installed at the Fort Hills mine complex in 2016. Since then, Rotaflow has been the single trusted partner to provide ongoing support for maintenance and routine weekly, monthly and annual inspections of the […]

Suncor Dredge Detailed Engineering Design

Suncor Dredge Detailed Engineering Design The Canadian government regulates tailing pond recovery in the Oil Sands by establishing a set of criteria for minimum recovery at each site, through “Directive 85”. Making the recovery of tailing increasingly difficult is the amount of organic matter, or “muskeg”, that is found in the ponds. The muskeg in […]

Scoping Study Deluge System Modification

Scoping Study Deluge System Modification Rotaflow has awarded a contract by Suncor in 2018 to perform a scoping study for modification of an existing deluge system at one of their plants in northern Alberta that consists of 17 zones. Rotaflow scope included preparation of a detailed hydraulic assessment of the system and evaluating different options […]